A tile reroof proposal includes “replace three pipe flashings.” Two pipes serve the plumbing system. The third exhausts an active radon mitigation system. Before a new tile layout prompts anyone to offset or shorten that pipe, the owner needs to know which installer is responsible for it and what evidence will close out the work.
Give the third pipe its own entry
Ask the mitigation contractor to identify the exhaust on a roof photograph and match it to the system label and operating instructions indoors. Mark the penetration on the tile layout. Have the roofer identify the flashing proposed for that tile profile. If the outlet would move, put the proposed position and nearby windows or air intakes on the drawing for the mitigation professional to assess before the tiles are cut. Assign responsibility for any interruption and return to service.
The roof photograph and the basement gauge tell different parts of the story. The photograph can document the finished weathering around the pipe. The U-shaped gauge found on many systems shows a pressure difference. An owner who photographs it before the work preserves a useful reference for the installer. That reading cannot tell the owner the radon concentration in an occupied room.
Make room for a result that arrives later
Suppose the replacement flashing is complete and the fan monitor appears normal. The closeout sheet can record the roofer’s completion and the installer’s operating check that day. Keep a separate entry for the indoor radon measurement, with the test location, dates, result and person receiving it. If testing is pending, give the owner the contact and expected reporting date. Copying the gauge reading into the test-result box makes the record look complete while leaving the indoor-air question unanswered.
Michigan’s environmental agency recommends regular indoor testing even in homes with mitigation systems. Follow the test instructions and the mitigation professional’s guidance for the home. For the separate roof-side issue of water passing a pipe, see the Guild’s guide to flashing over a concrete tile crown.