The plumbing drawing specifies the diameter of a vent pipe. The roofing submittal offers a flashing with the right opening. Even if the collar fits, the sheet around it still has to reach the right part of the concrete tiles. On a wavy tile, moving the pipe sideways changes the distance between the collar and the nearest raised crown.
Detail MC-02 in the Tile Roofing Industry Alliance manual gives two different ways to check coverage. On a flat tile the flashing must extend at least four inches onto the tile. On a profiled tile it must extend at least one inch beyond the crown. Measuring one inch from the pipe misses the reference point in the drawing.
Test the footprint before fixing the pipe location
Ask the roofer to lay out a short row of the selected tiles on a bench. Lay a full-size template of the proposed flashing over the row and mark the pipe centre shown on the plumbing plan. Trace the raised crowns on the template. If the sheet ends on the near side of a crown, the team can see the conflict while it can still consider a different flashing or coordinate a revised pipe position. Check any change against the plumbing design.
MC-02 also shows a flashing integrated with the underlayment at deck level. Record that detail before the tile covers it, then photograph the upper flashing against the finished profile. File both views under the same pipe identifier. If a dormer is nearby, also check its relationship to the vent outlet before approving a move.