A signed delivery ticket for 1,000 field tiles can be perfectly accurate while the crew working on a rear wing is 40 pieces short. The ticket counts what arrived. The foreman needs a second record showing which part of the job each group of tiles is intended to serve.
The Tile Roofing Industry Alliance’s MC-09 illustration gives an example of planning tile distribution by roof section. Project conditions, course layout and the tile itself matter. For material control, borrow the section-by-section accounting idea. The installer needs a separate, site-specific plan for safe loading and placement.
Reconcile the allocations before moving the material
Suppose the main roof needs 600 field tiles, the rear wing needs 350 and the agreed reserve is 50. The total is 1,000. If the marked allocations are 640, 310 and 50, the delivery balances exactly and the rear wing still has a 40-piece shortfall. Correct the allocation record before anyone requests an emergency order or moves heavy material unnecessarily.
Give each section a name that agrees with the roof plan. Keep field units separate from hip, ridge and other trim, and record pieces still held on the ground as such. When a section is postponed, note the location of its stock and who can release it. A quantity assigned on paper says nothing about how much weight a roof can safely receive. For stock intended for future repairs after completion, the Guild’s spare-tile reconciliation guide covers the handover count.