A storage record saying “120 spare tiles” can be misleading when some pieces are already promised to a repair, some await inspection and others are only on order. Before scheduling work, reconcile the stock by exact tile type and by availability. This is an inventory exercise, not a method for judging whether a tile is safe to reuse.
Separate physical stock from available stock
Consider this fictional example for one identified clay field-tile profile. It illustrates bookkeeping only; the quantities are not a recommended reserve or breakage allowance.
- Opening physical count: 120 pieces.
- New pieces received and checked into that stock: add 24.
- Pieces issued to completed work: subtract 18.
- Pieces physically remaining: 126.
- Of those, eight are quarantined for a specialist’s condition or compatibility review.
- A further 30 usable pieces are reserved for an approved upcoming repair.
Available, uncommitted stock is therefore 126 − 8 − 30 = 88 pieces. If another 40 are ordered but have not arrived, keep them on a separate “expected” line. They do not increase today’s physical count or the number available to a crew.
A later physical count of 124 would reveal a two-piece discrepancy. Investigate an unrecorded issue, breakage, miscount or movement to another storage location. Do not silently adjust the opening balance: record the correction and its reason so the next person can follow the history.
Do not combine unlike pieces
Maintain separate rows for field tiles, ridge fittings, hips and other accessories. A total of 200 assorted pieces does not establish that a particular repair has enough of the required fitting. Separate similar-looking profiles and unverified salvage until a qualified specialist has established the intended use.
The National Park Service’s Preservation Brief 30 explains why identification and compatible replacement material matter on historic clay roofs. That preservation guidance supports separating types; it does not prescribe this inventory formula or a universal reserve quantity. Inventory availability never substitutes for a roofer’s assessment of fit and condition.
Turn the count into a decision
For each row, record the identifier, storage location, physical count, quarantined quantity, committed quantity, available quantity, outstanding order and date checked. Add the person responsible for releases. When material returns from a job, verify its identity and condition before returning it to available stock.
Set any reorder trigger with the contractor and supplier using the actual planned work, replacement availability and lead time. Avoid assuming that past annual usage predicts storm damage or that all products can be reordered promptly. Confirm storage and handling arrangements with the professional responsible for the material.
This reconciliation complements the clay tile handover file. Use Tile Roofing USA for tile project resources. Keep natural-slate stock separately identified, with Slate Roofing USA as the corresponding resource.