A takeoff shows a 30-foot valley and three 10-foot lengths of copper. On the invoice the lengths add up. On the roof, part of each upper sheet covers the next sheet down. The order can run short even when the valley has been measured correctly.
For a real example of a joint requirement, the Town of Lincoln’s public library slate-roof bid set calls for individual valley sheets with at least eight inches of lap at transverse joints. A transverse joint crosses the channel where two sheets meet end to end. The lap under the field slates at either side runs in a different direction.
Count the joints, then subtract their shared length
Take an illustrative straight run of three 10-foot sheets. It has two transverse joints. With an eight-inch lap at each, 360 inches of stock gives at most 344 inches of installed length, or 28 feet 8 inches. A 30-foot run made from three pieces would need at least 31 feet 4 inches of developed length before any metal required at the head and outlet. A fourth piece would introduce a third joint, so adding a 16-inch offcut would still leave the order short.
Have the sheet-metal shop mark each piece and joint on a lengthwise sketch. Show any special end formations on that sketch and use the specified sheet lengths and connection details for the actual job. The separate valley taper drawing tells the slater where the side cuts run. It does not tell the shop how many feet of sheet to order.