A commercial building’s slate reroof is complete. The window-cleaning contractor returns with an old plan showing two roof anchors by a dormer. The handover photographs show new flashing at two posts in the same area. How will the owner establish that the documents and the posts refer to the same anchorages?
For a rope descent system covered by the US federal general-industry standard, OSHA requires the owner to provide written information about each anchorage to the employer before use. The statement must confirm that the owner has identified, tested, certified and maintained each anchorage for a load of at least 5,000 pounds in any direction per attached employee. The determination rests on an annual inspection by a qualified person and qualified-person certification as needed and at least every ten years. A roofing completion photograph records visible work. It cannot establish anchorage capacity or substitute for that documentation.
Reconcile the plan during the reroof
Before the slate is lifted, have the facility manager give the design team the existing anchorage plan and identifiers. Ask the contractor to record which posts were encountered and whether any anchorage, support or identifying mark was disturbed. Identify flashing work separately. Carry each location through to the final roof plan, including changes that make an old landmark hard to recognise.
If the records disagree, keep the anchorage out of use pending resolution by the owner and qualified professional. Record who holds the current written information and how the window-cleaning employer will receive it. Keep photos of the surrounding slates with the roof inspection record for the next repair.