A sheet-metal order reading “two valleys, 18 feet each” gives the shop a useful starting quantity. At the upper end of each run, though, someone still has to fit metal across the point where the roof planes meet. The length of the valley gives the shop no way to reproduce those angles.
The National Slate Association’s open-valley detail shows a shaped pan at the peak. It explains that this piece is usually formed on site so the folds fit the deck. A metal ridge covering may also serve at this junction, depending on the detail. If the valley quotation assumes the ridge contractor will close the peak and the ridge quotation ends at the last straight length, both estimates can look complete while leaving a gap in the scope.
Give the junction a place on the order
Circle the upper end of each valley on the plan. Against each circle, record the ridge finish, who supplies the closure and when the sheet-metal worker can measure the exposed junction. Where a shop will form the piece, agree who delivers the marked field template and who checks the fit before the slaters cover the edges. Two valleys with the same listed length may need different templates.
Carry this entry alongside the order for straight valley sheets and their laps. That lets the straight lengths proceed while the peak awaits its field dimensions.