The elevation shows a strip of flashing across the front of a dormer. The side section shows flashing beside the slates. At the lower corner both drawings stop at the outline of the wall. A sheet-metal shop could price every straight length on the plans and still have no drawing of the joint connecting them.
The National Slate Association illustrates a formed apron corner with overlapping metal and a soldered connection. The wall’s water-shedding layer laps down over the apron. These details answer separate questions. The metalwork has to turn the corner, and water draining from behind the siding has to reach the outside of it.
Ask to see the corner with the siding omitted
Request a sketch showing the front and side faces together, or have the shop fold a small sample. Mark the seam on both views. A line identifying the bend in a continuous sheet means something different from a line where two cut edges meet. Ask the fabricator which line is which and how the pieces join in the chosen metal. Then trace the lower edge of the wall wrap across that same corner with the installer.
Give the approved view to the siding crew as well as the slater. For a repeated dormer detail, photograph the first installed corner before cladding conceals the wall leg. Pair that image with the drawing when reviewing the remaining dormers. The Guild’s guide to concealed soakers on slate-clad dormer cheeks addresses the corner higher up the wall.