A merchant offers to supply only standard-width slates. The estimator expects the roofer to split a few down the middle to start alternate courses at the gable. Before accepting the offer, check what half the proposed width actually measures.
The Natural Slate Company advises using a slate-and-a-half where a standard slate would have to be cut narrower than 150 mm. With a 250 mm field slate, half the nominal width is just 125 mm. A slate-and-a-half is nominally 375 mm wide. It moves the first joint by the same half-width relative to the regular bond, while leaving a wider stone at the edge. The supplier needs to know about that piece while the order can still be changed.
Mark a single edge, course by course
Take a gable with 27 ordinary field courses reaching one straight verge. Suppose the approved layout puts a wide piece in the first of those courses and every other one above. Mark courses 1, 3 and 5 and continue through 27. That edge needs 14 wide pieces. If the layout starts with a full field slate and puts the wide pieces in the even-numbered courses, it needs 13. Neither count includes the under-eaves pieces, special top-course cuts or spares.
Repeat the count at the other end using the actual setting-out drawing. A dormer or a change in the verge line can interrupt the sequence. Show the wide stones as a separate item and remove the field pieces they displace from the field tally. Confirm the supplied width, length and hole positions with the slater before treating the count as a purchase order. A three-course joint sketch can help explain the bond where an edge meets a repair.