Two bids can both include “roof delivery” and leave the roofer with different work. The question to put to the carrier is concrete: when your operator finishes a lift, where are the tiles, where is the pallet and whose crew has handled the pieces? The answer belongs beside the delivery allowance before the installation crew is booked.
Florida supplier All Points Tile & Slate describes a crane service that presents palletized tiles at roof level. The roofing crew removes the tiles there. The supplier expressly says it does not deposit pallets on the roof. Reading only the service name could lead a scheduler to book the truck on Monday and the crew on Tuesday. Under the published arrangement the delivery depends on both being present together.
Give the quote a starting point and an endpoint
Ask the carrier to mark which slopes it can serve from the proposed truck position. Have the roofer identify who receives the tile and who moves it onward to the locations in the project’s loading plan. For a rear wing beyond the agreed service area, get a separate answer. A quote for the front slope leaves open the time and labor for that wing. Count ridge and hip fittings in the handoff as well as field tiles.
A booking note might read, “Carrier presents field tile to the receiving crew at the agreed front-slope position. Roofer supplies the receiving crew. Rear wing and boxed fittings require separate confirmation.” Replace those words with what both parties agree. The delivery description establishes a division of work. The project team still needs its site-specific lifting arrangements and approved loading locations before release.
At the end of the delivery, reconcile the quantities against the slopes actually served. The Guild’s roof-section delivery record gives the receiving foreman a way to distinguish pieces delivered to the property from pieces available to a particular crew.