Who releases the pipe organ before a church slate roof is opened?

Put the organ builder into the roof programme early enough to protect the instrument, price the work and plan its return to use.

By the Slate, Tile & Metal Guild ·

A parish asks for a price to strip the slates above the chancel. The roofer allows for protecting the pews and clearing the floor each day. The organist expects to play on Sunday. Before accepting either assumption, bring the organ builder to the planning meeting. Cleaning visible surfaces below the work and protecting the airways of a pipe organ are different jobs.

The Diocese of Exeter warns that dust collecting inside pipes and air ducts can cause serious problems during church building work, including work outside. Give the organ builder the roof plan and proposed sequence. Locate the console, pipe chambers and air supply on that plan. Ask which parts could be affected when the roofers open the first bay and whether the instrument can be used while protection is in place. A covered console alone tells the parish little about conditions in a chamber high above it.

Price both visits

Ask who will install the protection the organ builder specifies, who may disturb it and what evidence the parish should retain. Include the return visit in the tender. Give that visit a trigger the site manager can recognise, such as completion of dusty work and cleaning of the surrounding area. Finishing the slate courses above the organ might precede ceiling repairs below them by weeks.

For a phased job, record the last service before the instrument is taken out of use and who will tell the organist it can be played again. If a separate contractor opens the ceiling later, ask the organ builder to revisit the plan. Keep these arrangements alongside the schedule for protecting the roof space so each trade can price its own work and the parish can arrange music for the affected services.

Further reading

Diocese of Exeter · Guidance on organs, protection during building works. The diocesan guidance addresses dust during both internal and external works. The scheduling example is hypothetical.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles