On an estimate for a historic slate roof, “remove and reinstall ornament” sounds like one operation. On a gilded ridge it leaves an important decision unanswered. Who decides how much of the surviving finish is to be kept, and when will that person see it?
Read the roof and the finish together
The Château de Versailles describes two parts of the Royal Chapel restoration. Roofers removed damaged slates, leadwork and sculpted pieces. The roof account places the return of the ridge sculptures and gilding among the finishing operations. In a separate account of the gilder’s work, the estate explains that surviving gold might be cleaned and consolidated, while another surface might call for complete regilding. A picture taken after completion would tell you little about which treatment a particular piece received.
Give each piece a handoff record
Before removal, ask the conservation team to pair an overall ridge elevation with close views of each ornament. Identify its position and orientation, the supporting metalwork and any areas of surviving finish the conservator wants protected. Put the same identifier on the handling record and on the photograph. A row of nearly identical ornaments can still contain one with a different repair history.
Then assign the decisions that fall between trades. Who accepts the piece into storage? Who records its condition on arrival? Who approves the support before the sculpture returns? Ask the gilder and roofer to agree where the finish work will happen and what access they will still need. Recording that agreement before scaffolding comes down gives the owner a way to check whether the price includes the final visit.
At handover, request one view of the reinstated piece in context and the treatment record for that same identifier. Keep these with the slate roof inspection report so a future repair team can distinguish damage to the covering from a change to the ornament or its finish.