When a contractor prices a dormer ridge repair by the metre, look at the point where the short ridge dies into the main roof. A drawing with three ridge lines meeting can suggest that three lengths of roll simply meet there. On a concrete-tiled roof using Marley's RidgeFast system, that reading misses the saddle under the adjacent tiles. It also misses a decision about when the flashing trade needs access.
Marley's UK guide describes a T-shaped ridge junction or a dormer ridge meeting the main slope. Its RidgeFast construction stops at the valley. The guide calls for a Code 4 or 5 lead saddle to go in before the roof tiles. At a T, the corrugated edge of the roll across the head adheres to the saddle. The roll approaching along the leg stops short of the mortar bedding, and the end ridge tile needs a mechanical fixing.
Agree on the handover before the surrounding tiles go back
On the roof plan, ask the contractor to mark the dormer approach, the valley and the tiles that must be lifted to expose the saddle position. The repair price should identify who lifts and reinstates those tiles, who forms the saddle and who completes the ridge. If the price covers only ridge units, resolve access to the underlying flashing before comparing it with a price that includes both trades.
Arrange a photograph with the saddle still exposed, referenced to the dormer on the plan. A second view can show the roll termination before the end ridge unit conceals it. A finished view alone cannot show when the saddle was fitted. For the broader estimate, the Guild's junction-counting guide explains how to keep individual junctions visible alongside linear quantities.