A shop can form a cap that fits the width of a parapet perfectly and still leave the last course of concrete tile short of cover. The shop measures across the top of the wall. The roofer sets the upper edge of the field tile on the sloping face. A section through the two pieces shows what a plan dimension misses.
In the metal-cap option of the Tile Roofing Industry Alliance’s MC-18C detail, the cap extends at least four inches over the field tile. The water-protective layer continues over the wall top. The drawing also illustrates a different finish using trim tiles over a nailer. A change from tile trim to sheet metal therefore needs more than a colour selection.
Release the cap from a section
Ask the roofer to mark the upper edge of the installed field course on a section through the wall. Have the fabricator draw the lower edge of the cap on the same section and dimension the cover over that course. On a profiled tile, include a piece of the actual tile at the trial fit. Record any change in the wall build-up between the measured sample and the final assembly.
If the cap is already on order when the top course moves, return that section to the shop before it bends the remaining lengths. A dimension taken down from the wall top can remain unchanged while the cover on the tile decreases. At the other end of the slope, the pitch-break section records a separate junction.