Which photos must precede the tile on a FORTIFIED roof with taped deck seams?

Schedule the seam, anchor-sheet and cap-sheet photos while each layer can still be seen.

By the Slate, Tile & Metal Guild ·

On a phased tile reroof, a finished front slope and a freshly taped rear slope can be visible on the same day. A photograph of each side at completion will show the tile color and layout. It cannot recover the attachment pattern already covered on the front slope. The crew needs a photo schedule tied to the order of work.

For a home pursuing the 2025 FORTIFIED designation using taped deck seams and underlayment, the IBHS checklist identifies several distinct views under section 4.4.1.1. It calls for an overall view from each of four elevations after seam taping, then another set after the underlayment or anchor sheet is installed. It also asks for two close views of the nailing pattern. For a tile covering, it asks for four elevation views of the installed cap sheet.

Use one row per elevation

Before work starts, put the four elevation names down the left side of the schedule and the three visible stages across the top. Give the two nailing close-ups their own file entries. A close view that shows the fasteners clearly may be impossible to locate later. Include the slope identifier in the filename and pair it with an overall image. Keep legible product-label photographs with those records.

Have the evaluator confirm the applicable checklist and how to document partial slopes before the first batch of tile covers the work. If the east elevation was photographed after taping but missed at the cap-sheet stage, mark the specific missing view and ask the evaluator how to proceed. Four photographs from the west side cannot supply the east-side record. This sequence applies to the selected method. Other sealed-deck methods have their own documentation requirements. File the evaluator’s record alongside the owner’s tile roof handover documents.

Further reading

Insurance Institute for Business & Home Safety · 2025 FORTIFIED Home Documentation Requirements, new roof checklist. The cited document sets out the relevant authorization or documentation requirements. Project examples are hypothetical.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles