A takeoff for a concrete tile roof shows a 5.8 m valley. The supplier offers two 3 m trough sections. The order appears to have 200 mm to spare until the estimator draws the joint. Part of the second trough occupies the same stretch of valley as the first.
Hambleside Danelaw’s installation sheet gives different overlaps for different roof pitches. For its specified system on a 25-degree roof, the sheet gives 300 mm. The two pieces would cover 3.0 + 3.0 − 0.3 = 5.7 m. That is 100 mm short of the stated run even before any trimming at the ends. At 35 degrees the same table gives 200 mm. That would leave exactly 5.8 m, with nothing left for end cuts.
Draw the joints on the measured run
Ask for the distance along the valley itself. On a sketch, place the eave end, the head termination and every proposed joint. Write the roof pitch beside the manufacturer’s overlap entry and carry the overlap once for each joint. If the valley runs into another at a dormer, give the intersection its own detail so a saddle or cut end does not disappear into a total of linear metres.
Keep the proposed cut list with the tile valley detail. If the supplier substitutes a different trough, have the estimator redo the joint calculation from its instructions. Adding a section changes both the available stock length and the number of overlaps.