A ridge replacement can affect a second system that runs along the same line. If a lightning-protection conductor follows the ridge, the owner needs to know how its holders attach before the old ridge tiles come off. Buying the same number of new caps does little to answer that question.
DEHN’s range illustrates the distinction. Its FIRSTsnap holder attaches to a dry ridge’s tile clip. The catalog specifies an 8 mm round conductor for that holder. The same catalog lists a different clamp with a spacer and seal, with different supported conductor dimensions. The words “ridge conductor holder” on a parts list do not identify either attachment. These are examples from one supplier’s international range. A project’s lightning-protection specialist should select and detail the system for that building.
Agree on the handoff before removal
Have the roofer identify the replacement ridge tile and its fixing hardware. Give that detail to the lightning-protection contractor together with a record of the existing conductor route and holders. If the existing holder relies on a clip that disappears in the new detail, have the specialists resolve the interface before ordering replacement holders or approving a price for reuse.
The work order should name who handles the conductor during roofing, who reinstates the system and who documents its inspection afterward. Include that sequence in the occupied-building roof work plan. The owner can then tell when the roofing crew has finished and when the lightning-protection work is complete.