A roofer proposes an extract terminal that matches the concrete tiles. The mechanical schedule gives an airflow. The supplier gives a pressure loss. Before comparing either number with the fan selection, ask which flow the supplier used to obtain that loss.

Marley’s table for its Double Roman terminal gives 6.5 pascals at 15 litres per second and 24.8 pascals at 30 litres per second. Suppose the project calls for 30 litres per second. Copying the first pressure figure into the substitution request would understate the terminal loss by 18.3 pascals. Simply doubling the first figure would still miss the published value.

Send one complete row to the mechanical reviewer

Identify the proposed terminal model, the design flow and its units, the corresponding pressure loss, and the document used. If the required flow falls between the listed points, ask the manufacturer for applicable data. Leave the fan decision with the designer who knows the rest of the duct route. The opening area printed elsewhere on the sheet cannot supply the missing pressure loss.

The roofer can then settle the profile and weathering detail while the mechanical contractor checks the airflow. Put both decisions against the same terminal model in the bid comparison. If the proposed terminal changes again, the reviewer can see exactly which calculation needs another look.

Further reading

Marley · Tile Vent Terminals, pressure resistance table. The figures apply to the named Marley terminal and stated test flows. A mechanical designer must check the selected terminal with the complete fan and duct system.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles