What should the roofer photograph before solar panels cover the tile hooks?

A side view at a representative hook can show whether a solar mounting bracket clears the profiled roof tile beneath it.

By the Slate, Tile & Metal Guild ·

In a handover photograph taken from above, each solar hook appears to emerge neatly between two roof tiles. That view shows where the hooks are. It can hide the small space under the arm where it passes over the tile. Once the rails and modules are in place, it can be difficult for the owner to obtain that view again.

Consider the illustrated K2 Tile Hook 3S Wide Base, part 4001294. Step 3 of its instructions calls for at least 5 mm between the bracket and the tile at the indicated location. A photograph with a tape held vertically beside the rail measures a different dimension. Even a clear view of the bracket where it attaches to the roof can miss the point where its arm comes closest to the tile.

Agree on the view before the crew covers the hooks

Ask the solar installer and roofer to identify the hardware and tile profile used on each roof plane. On the first representative installation, have the crew record the specified gap at the point marked on the manufacturer’s drawing, with the surrounding tiles in their final position. Keep the measured detail with a wider location photo and the hook part number. If the addition has a taller roll than the main roof, include an example from that area too.

Suppose two measured locations show 6 mm and 4 mm for this part. An average of 5 mm would conceal the second location’s shortfall. Ask the installer to document its disposition and verify the remaining work to the project requirements. The photographs record the tile interface only. The mounting design still needs its own verification of attachment and loads. The tile roof solar coordination guide gives context for the other roof details in the handover file.

Further reading

K2 Systems · Tile Hook 3S Wide Base, part 4001294, installation instructions, step 3. The dimension belongs to the illustrated K2 assembly. Confirm the current instructions for the hardware, roof profile and region on the project.