A supplier’s list for a slate roof shows eight end collars next to a drawing with only two eaves. Before striking four collars from the order, count where the pipes end. A run with two horizontal pipes has two ends on the upper pipe and another two on the lower pipe.
Alpine SnowGuards offers a two-pipe configuration of its PP125 system for natural slate. Its accessory schedule calls for a collar at each pipe end in each run. The collar keeps the pipe from sliding through the brackets. The cap closes the open mouth of the pipe, and a coupling connects sections. All three parts may look like something that belongs at a pipe end when they appear as short descriptions on an invoice.
Count on the elevation
On a drawing with one two-pipe run on the north eave and one on the south, mark four terminal points on each eave. That explains the eight collars. Joining shorter lengths within either run adds couplings at the joints. If the designer splits one of the runs into two, trace the new ends and update the collar count. Alpine limits an uninterrupted run to 100 feet to accommodate thermal movement. Have the system designer locate any required breaks and detail the brackets.
Keep the marked elevation with the hardware schedule. Add the selected roof covering and project-specific bracket detail so the installer can match the rail to the slating scope. A property owner arranging that work can find natural slate contractors through the Guild directory on Slate Roofing USA.