A summer slate repair meets a known bat roost. What goes on the schedule?

Identify the affected roof area and get local wildlife guidance before fixing the start date for work around an occupied roost.

By the Slate, Tile & Metal Guild ·

A building committee wants to repair loose slates beside a louver during summer recess. The caretaker has seen bats leaving that louver in the evening. Put that observation on the scope drawing before promising a start date. An allowance for replacement stone will do little to cover a crew booked for a week when the affected opening must remain undisturbed.

Wisconsin’s Department of Natural Resources illustrates why place and timing matter. Its cave bat conservation plan describes restrictions on building work that could affect a known roost during June and July, when flightless young may be present. The document separately addresses bats discovered unexpectedly during roofing. These are Wisconsin provisions. Obtain the current advice for the building’s location and circumstances before scheduling work that could affect the roost.

Put the wildlife decision ahead of the roofing mobilization

Give the wildlife professional the roof plan and the actual repair scope. Identify whether the work involves only a distant roof face, opening the louver surround, or closing gaps at the eaves. Record the observed location and dates, who will assess the impact, and which activities may proceed under the resulting advice. The roofer can then say whether the permitted areas are accessible as a separate phase.

Include a contact and a pause procedure for unexpected discoveries in the site instructions. Leave wildlife handling to qualified personnel. When seeking a slate roofing contractor, ask for separate mobilization costs if the wildlife review calls for two visits. That gives the owner a practical budget for the agreed work window.

Further reading

Wisconsin Department of Natural Resources — cave bat conservation plan, section F on building projects. The cited document describes its own project or geographic scope.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles