Slate reroofing · Drainage handover

After the slate work, is the lower roof’s siphonic drain complete?

Identify the removable air baffle before protecting a lower roof during slate work, and give the drainage contractor a record to check before handover.

By the Slate, Tile & Metal Guild ·

A low flat roof below a slate slope makes an obvious landing place for chips during stripping. The repair scope may already require the roofer to protect the lower covering and clear its outlets. If that roof drains through a siphonic system, add one question before access begins: which removable parts belong to each drain?

Pipelife’s system guide describes an outlet with a removable air baffle. Under light rainfall the system drains by gravity. Under heavier flow the outlet is designed to limit air entering the pipe so that siphonic drainage can develop. A little water disappearing down the drain after the slate debris has been cleared demonstrates an open path at that flow. It does not establish that the correct baffle is present or that the system will perform as designed in a storm.

Give each outlet its own handover record

Before the slate work starts, have the building’s drainage contractor identify the outlets in the affected area against the drainage drawing. Give each a location, a photograph from above and a component reference from the actual system manual. Record a missing part at this stage so the owner can distinguish a pre-existing defect from something displaced during the work.

Agree how the lower roof will keep draining during stripping and who may remove or refit a component. At handover, match the reassembled outlet to the original record and its specified parts. A generic basket that fits the opening is insufficient evidence of compatibility. Ask the drainage contractor to resolve discrepancies and specify any further checks before signing off. For the separate question of where water goes if the primary system cannot carry it, see the Guild’s guide to tracing an emergency overflow.

Further reading

Pipelife — Siphonic Roof Drainage: Design and Specifications, roof outlet description. Pipelife describes its own flat-roof outlet. The work sequence is a suggested handover for a lower roof beneath slate repairs.