Slate project scheduling

When should gutter brackets arrive on a historic slate reroof?

A National Park Service reroof sequence shows why a late gutter installation can need hardware early.

By the Slate, Tile & Metal Guild ·

The gutter installer may be booked for the last week while some of the gutter hardware belongs on site in the first. In a reroof documented in National Park Service Preservation Brief 29, the crew fitted brackets as it laid the slate. The gutters and snow boards themselves went on at the end. That order allowed the supports to be in place before the roof covered their attachment locations.

Suppose a bid schedule shows the north slope closing on Thursday and a single delivery marked “gutters” the following Monday. Take the project’s eave detail to the scheduling meeting. Where does the bracket attach? What will cover that point on Thursday? If the design calls for a concealed support, give the brackets a delivery date of their own. Name who supplies them, who sets them and who checks their location before the slaters move past the eave.

Fascia-mounted hardware may produce a different schedule. Use the specified attachment to set the sequence. Related background is available in Slate Roofing USA’s guide to snow retention.

Further reading

National Park Service — Preservation Brief 29, illustrated reroof sequence, photograph (i). See the cited source for the scope of its guidance.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles