Preserving the craft. Building its future.

Slate · Estimating

Did the slate quote pick up the last bid amendment?

Trace one change in a federal invitation for bids from the revised slate schedule to the supplier’s quote and the prime bidder’s acknowledgment.

By the Slate, Tile & Metal Guild ·

Imagine opening a supplier’s quote on bid morning. It includes 40 roofing squares for the main wing, exactly as the original drawings showed. Yesterday’s amendment added six squares for a connecting roof. The quarry can still meet the requested delivery date. Does the prime bidder have what it needs to submit? Two records matter here: the scope behind the price and the bidder’s acknowledgment to the agency.

Trace the six squares through the estimate

Give the supplier the amendment number, issue date and revised sheet. Ask for a dated revision that identifies both roof areas and states whether freight changes. In this example the field area is now 46 squares before any separately agreed allowance. If the quote says 46 squares but the estimate still adds a six-square alternate, the bidder would count the connector twice. Strike the superseded line in the working comparison and retain the original quote with its date.

A change in area can also leave the supplier short of information. If the connecting roof has a different slate size and the amendment gives only its area, flag that exact question through the invitation’s designated inquiry process. An estimator should be able to tell which part of the number is firm when the deadline arrives.

Close the acknowledgment separately

For a federal invitation incorporating FAR 52.214-3, the bidder must acknowledge the amendment using a permitted method, and the government must receive the acknowledgment at the specified place by bid receipt time. A supplier’s revised quote sent to the general contractor updates the pricing file. The prime still needs to check its own submission. Put the issued amendment, revised quote and submission record under the same amendment number so the team can recover all three later.

For the earlier step of keeping area, pieces and allowances consistent, see Slate Roofing USA’s guide to slate quantity units.

Further reading

Federal Acquisition Regulation 52.214-3 — Amendments to Invitations for Bids. Check the provisions and submission instructions in the specific invitation.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles