On a slate reroof with a slate-hung gable, a scaffold tie can occupy the very spot where the slater needs to finish the wall. The roofer’s completion date and the scaffold collection date may look compatible on a programme. If the slater leaves first, the owner may discover several small openings only after the working platform has gone.
Ask the scaffold provider to mark on a gable elevation every tie position that affects the slating. Number each position. Next to each number, the slater can record which courses will remain open, what protection they need during the work and which replacement pieces have been reserved. A photograph taken before opening up will help where the wall carries a pattern or more than one slate size.
Price the return visit while access is being planned
Have the scaffold contractor and slater agree how competent workers will reach each opening to complete the repair. The UK Health and Safety Executive describes removing ties in stages as a scaffold is dismantled. Where a tie must be removed to let work proceed, its guidance requires an equivalent tie nearby to maintain stability. A mark on the slater’s elevation identifies unfinished work. It gives no authority to move the tie.
Use the numbered elevation at handover. For each position, record completion of any repairs behind the slates, the finished face and the date. If a location stays open, name the responsible trade and record the agreed access arrangements before releasing that phase. The scaffold planning guide covers the broader sequence where several trades share access.