A slate roofer may have stone on hand and a scaffold booked for Monday, yet still be unable to start at the eave. An overhead wire runs from the pole to the building beside the proposed work platform. Include that crossing when the roofer plans access. If the utility needs to disconnect service, two appointments can govern how much of the roof the crew can open that day.
Pacific Gas and Electric specifically includes roofers among those who can request a temporary shutdown. Its residential project guidance advises allowing approximately 30 business days to schedule. It asks for both the desired disconnect and reconnect times, whether the utility must stand by, and any obstacles to access, including locked gates. Check with the utility serving the site for its timing and instructions.
Work backward from reconnection
Suppose the slater needs access to two courses beside an electrical attachment, and an electrician also needs time at that spot. Ask both trades what must be finished before the utility can return. Who will meet its crew? What happens if lifting the slates exposes rotten fascia and the work takes a second day? Agree who will call the utility and notify occupants if reconnection has to move.
Make the utility’s confirmation a condition for work in the affected area. A scheduled time or a dark building gives the roofer no assurance that the overhead line is safe. Show the affected part of the eave on the scaffold access plan so the crew can see which work depends on that confirmation.