Find a dormer on the roof plan and trace its little roof. Now turn to the side elevation. If the wall between that roof and the main slope is also clad in slate, which line of the estimate pays for it? A takeoff can account for every sloped roof plane and still miss both cheeks of every dormer.
Measure the shape you see from the side
Suppose one cheek has a horizontal top edge, a straight sloping bottom edge and vertical ends 5 feet apart horizontally. The exposed heights at the ends are 4 feet and 1 foot. On that elevation the average height is 2½ feet. Multiply by 5 feet to get 12½ square feet of wall. Two identical cheeks on each of four identical dormers would add 100 square feet of gross cladding. Check both sides on the drawings before multiplying. An adjoining roof can hide part of one cheek while leaving the other fully exposed.
That example adds up to a roofing square in area. It does not tell the supplier which pieces to ship. A slanting lower edge introduces cuts, and the wall schedule may specify a different slate size or pattern from the roof. A window or stepped cheek changes the shape again. Break an irregular outline into measurable parts and show any deduction separately so the next estimator can reproduce it.
Give the wall its own line on the quote
Record the dormer identifier, elevation drawing and revision, gross cheek area, deductions and specified cladding. Ask the slater which sizes and cut allowances that geometry requires. If siding is by another trade, name the responsible trade on the line. That single entry lets the contractor distinguish an intentional exclusion from a missed surface.
The Slate Roofing USA field calculator can help check the main roof quantity. Keep the cheek worksheet alongside that calculation so the two scopes stay visible when a dormer changes.