A school district may have a well-maintained asbestos management plan and still lack an answer about an old roof covering buried under natural slate. Look at what the inspector was assigned to examine. EPA’s guide for school asbestos coordinators explains that the school inspection under AHERA excludes exterior materials such as roofing and siding. An empty roof entry therefore cannot establish what is in a concealed layer.
Match the report to the demolition drawing
Suppose the bid calls for saving the field slates, stripping the underlying covering and replacing flashing at a parapet. Mark all three operations on a roof plan. For each one, ask the district’s designated person and qualified asbestos professional what existing documentation identifies the materials the operation would disturb. A school-wide inspection date tells bidders little if a referenced sample came from a different wing or stopped at the interior ceiling.
Keep the source document, location and layer together. An entry might read “science wing, west parapet, concealed roof layers; no applicable determination located in records reviewed.” That describes the information gap without guessing what the material contains. Give the question to the qualified professional before intrusive work. Leave sampling and the decision about how to proceed with that professional.
EPA separately explains the inspection requirements for the area affected by a renovation under the asbestos NESHAP. Have the district’s team address applicable federal, state and local requirements and issue the resulting scope to all bidders. Once the materials question is resolved, coordinate the occupied wing’s air intakes with the actual work limits.
