How many square metres does one crate represent in a slate environmental declaration?

Convert a crate-based figure to the area represented in the declaration before comparing roofing options.

By the Slate, Tile & Metal Guild ·

An architect’s carbon worksheet has one row per square metre of roof. The supplier’s environmental product declaration reports impacts for a wooden crate. Copying one of those impact values directly into the worksheet would assign a whole crate to each square metre.

BRE Global declaration 000472 describes a crate holding 1,223 kg of roofing slate, approximately 800 pieces. It gives an average of 21 pieces per square metre. Using those assumptions, the declared crate represents about 38.1 square metres (800 divided by 21). For an indicator reported per declared unit, divide the crate result by 38.1 to express that same indicator per square metre on the declaration’s basis. Keep the original units and life-cycle stage beside the converted result.

Keep the source calculation visible

Attach the declaration and show the two quantities used for the conversion. A future reviewer can then see why the denominator is 38.1. The piece count is approximate, so carrying the result to several decimal places suggests precision the source never supplied. There is also no reason to round the crate count up to the next whole shipment in a comparison of one square metre of installed roof.

When reviewing an actual project, record the proposed slate size, headlap, coverage and waste assumption alongside the comparison. A different layout can change the mass of stone needed for the same covered area. Ask the person preparing the assessment to reconcile those differences and the stages included in each declaration before ranking the options. Keep the calculation with the slate material submittal so a later substitution prompts a fresh review.

Further reading

BRE Global · Spanish Slate Quarries UK Ltd, environmental product declaration 000472, declared unit. The conversion uses the average quantities in this particular declaration. Project geometry and purchase quantities can differ.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles