Preserving the craft. Building its future.

Concrete tile · Scheduling adhesive work

The air has warmed up. Is it time to set the concrete roof tiles?

Use the product, air and surface readings to decide when to release an adhesive-set tile operation on a cool morning.

By the Slate, Tile & Metal Guild ·

At a morning coordination meeting the forecast shows 60°F. The concrete tile crew wants to begin on a shaded slope, and another trade has booked access later in the day. Before releasing either slot, ask which temperature the forecast actually answers. It describes outdoor air. The adhesive that spent the night in storage and the surface where it will be applied each have their own temperature.

For example, DuPont’s Tile Bond booklet recommends a product temperature of 70–90°F at application. It calls for both the ambient air and the surface to be at least 50°F and rising. The same booklet gives a different range for storage. A note that the cylinder was stored correctly overnight leaves the application question open.

Write down three readings and the next decision

Imagine an installer records air at 58°F and rising, a shaded application surface at 47°F, and adhesive at 74°F. The adhesive is within the recommended product range. The surface is below the stated minimum. Put the location on the work plan, leave that area pending and have the installer recheck conditions there. A warmer reading from the sunny side of the house cannot clear the shaded slope.

At the next check, record the time, roof area, product identification and actual readings. Ask the installer to confirm surface preparation and cure requirements before releasing access for the following trade. Keep this entry alongside the tile installation checkpoints. On the next cool morning, the superintendent will know which conditions to verify and whose decision to obtain before moving the schedule.

Further reading

DuPont · Tile Bond Roof Tile Adhesive, Operating Instructions and Maintenance, storage and application conditions. Temperatures apply to the cited Tile Bond instructions. Confirm the selected adhesive, current approval, installation guide and project conditions with the installer.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles