At the wall separating two homes, a tile drawn as a straight line can hide the largest opening the firestop has to address. Look across a profiled concrete tile: the underside rises under each roll. If the wall-head detail ends its dimension at the low part of the tile, the number can look reassuring even when the specified product is outside its stated range.
Tenmat’s instructions for its RTF roll define a maximum gap of 96 mm from the wall head above the breather membrane to the highest point on the underside of the tile. Imagine a section measuring 82 mm at the low point and 101 mm under the crown. Of these two measurements, 101 mm governs this particular check. It exceeds the stated maximum by 5 mm. Averaging the two values would conceal the problem.
Return the question to the designer before closing the roof
Mark the compartment wall on the roof plan. At that location request a section with the actual wall head, membrane, battens and tile profile, showing the measurement endpoints. Include the proposed tile model and whether a separate ridge detail occurs along that wall. Give the architect or fire engineer the drawing and the firestop manufacturer’s applicable system evidence. A change in tile profile after approval can change this dimension even if the wall height stays the same.
The data sheet also limits the system to suitable rated walls or spandrel panels with noncombustible tiles. Passing a single dimensional check cannot establish the performance of the completed junction. Keep the designer’s disposition with the roof records. The guide to roofing fire classifications provides background for reading a separate covering or assembly rating on the roof schedule.