Can a slate holing jig justify a four-at-a-time labour allowance?

Price the hole locations, handling and tool cycle against the selected supplier’s preparation instructions.

By the Slate, Tile & Metal Guild ·

A jig can locate nail holes consistently. Whether it permits drilling a stack of slates in one operation is another question. It matters when comparing a price for pre-holed material with a cheaper price for blanks and an allowance for drilling on site.

SSQ’s natural slate fixing guide tells users of its drilling method to drill one slate at a time. It separately discusses the adjustment and maintenance of punching equipment. A subcontractor offering a template for repeated hole positions has therefore answered a layout question. For work following that guide, the labour allowance still has to cover handling and drilling each piece.

Read the small print in the production rate

Suppose the repair needs 120 unholed pieces of one size. An estimate assumes that four pieces go into the jig together and allows 30 loading cycles. Under the single-piece method the same order has 120 individual loading cycles. That arithmetic does not multiply the entire labour bill by four. Setting the template, checking the first piece and packing the finished stock may take the same time under either estimate. Ask for those operations on separate lines, then have the crew time a representative run with the actual blank and approved equipment.

Before timing, agree where the holes must fall on the roof. A fast process with the wrong gauge produces a stack of unusable pieces. For a repair over open battens, use the existing support positions to settle that question first. Carry the measured shop rate and the quantity requiring preparation onto the comparison sheet so the delivered prices and labour allowances share the same scope.

Further reading

SSQ — Natural Roofing Slate Design and Fixing Guide, nail fixing and holing. SSQ gives the preparation guidance. The labour comparison is an illustrative tender check, with no assumed production rate.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.