A salvage tally lists “short Mission tiles, 48.” That line does not tell the estimator whether there are enough pieces to restart a roof at the eave or finish it at the ridge. In a two-piece Mission system the pan forms the trough, and the cover spans the joint. A shortened piece still has one of those two jobs.
Trace one trough from bottom to top
In Ludowici’s laid-tight Mission detail, the eave uses short covers over regular pans. At the last course the arrangement reverses: the pans are shortened and the covers are regular. The manual distinguishes this from a staggered Mission field. A roof with an intentionally irregular lower edge needs its own identification before anyone applies the laid-tight schedule.
Suppose the salvage rack holds 36 short covers and 12 short pans. A purchase request for 24 of each has a shortfall of 12 pans, even though both totals equal 48. Separate the two profiles on the tally; also keep actual eave closures and ridge fittings on their own lines. This arithmetic assumes the pieces are sound and compatible, two checks for the tile specialist before the stock is allocated.
Ask for an end-view photograph of each loose sample alongside its original row location. On the order, label the lower or upper course, pan or cover, profile and confirmed dimensions. Where the original stock cannot be identified, the Tile Roofing USA matching guide gives the supplier more to work with than a count of short pieces.