A building manager preparing a roof tender might write “attic inspected, no bats observed.” At Acadia National Park’s Brown Mountain Gatehouse, that statement would have missed an important part of the building. Researchers found no evidence of roosting inside the buildings, yet documented daytime roosts underneath the exterior clay tiles.
Map what the survey actually covered
The park’s team distinguished sheltered night roosts between towers from enclosed day roosts beneath tiles. That distinction changed the repair question. Even if a new tile reproduced the old roof’s appearance, would the work preserve the spaces the animals used? The park described a plan to retain those spaces with an in-kind repair and to schedule the work around local roost use.
For a different building, start by marking the limits of the existing survey on the roof plan. An interior visit covers the rooms entered. A ground observation covers the elevations visible at the time. If a tile strip will be lifted above a courtyard that nobody examined, name that strip in the work description and ask the project’s wildlife specialist what assessment is appropriate before access or disturbance.
Give the scheduler an answer they can use
Suppose a contractor offers a single mobilization date for the courtyard and street wings. Ask for a schedule that identifies when each wing becomes available, who confirms release and which tasks can proceed elsewhere if one wing needs more review. At Acadia the project team identified a local seasonal window. Copying its dates into another building’s contract would leave the underlying site question unanswered.
A useful bid clarification records the affected area, the person coordinating wildlife review and the decision the roofer needs before lifting tiles. Keep any conditions with the drawings used by the crew. The park’s account is a public example of coordination, not an installation specification. For the separate question of conserving the covering itself, see Tile Roofing USA’s historic clay tile guide.