Preserving the craft. Building its future.

Concrete tile · Project scheduling

The concrete tiles are late. Which roof section runs out of exposure time first?

Use each roof section’s underlayment installation date to check a delayed covering schedule against the applicable product limit.

By the Slate, Tile & Metal Guild ·

A revised programme says the concrete roof tiles will arrive in six weeks. The underlayment on the west wing went down well before the membrane on the east wing. A single site-wide date for “roof dried in” hides which section has been exposed longest.

Miami-Dade County’s Notice of Acceptance 24-0919.02 is a specific example. It limits the time its named Westlake Royal TileSeal HT and MetalSeal HT underlayments may remain exposed as a temporary roof to 180 days from application. The date the rolls arrived on site answers a purchasing question. The date the sheets were applied starts the exposure calculation under this document.

Track the day each section will be covered

Suppose the west wing has been exposed for 120 days. Delivery six weeks from now would put it at about 162 days. If the contractor needs a further four weeks before the last section there is covered, that section would reach roughly 190 days. A delivery that looks on time against the membrane limit can still leave part of the roof exposed too long.

Mark application dates and planned cover dates on the roof plan. Check the product and governing documents for each area. Ask the contractor to identify sections needing an earlier work sequence or written direction from the designer and manufacturer. The maximum exposure period is only one limit. Damage or an installation defect can need attention sooner. File the revised plan with the tile roof underlayment records.

Further reading

Miami-Dade County — NOA 24-0919.02, general limitations for TileSeal HT and MetalSeal HT. The cited example applies to the identified project or product.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles