On a concrete tile reroof, moving the pool heater’s return pipe can give the roofer space to finish a valley. The revised line may still carry water while the pump runs. What happens to the water left inside when the pump stops?
Heliocol’s residential manual asks designers to provide a way for water to drain from roof-mounted collectors. It favours gravity drainage and calls for a means of manual drainage where automatic drainage cannot be achieved. It also directs installers to obtain mounting guidance for concrete tile. A diagram of brackets for a shingle roof cannot establish the pipe elevations on the finished tile assembly.
Follow one pipe all the way off the roof
Have the pool-system installer mark the collectors, supply and return on a roof plan. At each proposed change of direction, add a side view showing the height of the supports above the finished tiles. A line routed below an obstruction and then lifted back up can form a pocket. It may look like a straight run when viewed from above. Ask how that pocket empties, and where a person could reach any required drain.
Have the roofer and pool installer agree on the route before the equipment goes back on the roof. The pool installer’s handover should identify the drainage method and any seasonal operation the owner must arrange. A successful circulation test with the pump running answers the heating question. Documenting drain-down answers the separate question raised by the rerouted pipe.