A product approval in a concrete tile roof binder may identify the tile and the attachment system accurately. An owner reviewing the binder still needs to know what happened on this particular building. A document issued before the crew started cannot record a field test performed after installation.
Miami-Dade County’s published roof inspection checklist illustrates the distinction. On the final inspection page for roofing permit 107, it calls for field verification and a static uplift test under TAS 106 for adhesive-set and mortar-set tile systems before final inspection. Confirm the current requirements with the permitting authority for the specific permit and attachment method. A checklist from Miami-Dade cannot settle a closeout question in another county.
Match the record to the roof
Consider a binder containing a manufacturer’s approval and an undated photograph of a test instrument. Ask for the project-specific field record. Look for the site and permit number, test date, person responsible, locations tested and results. If an initial result led to corrective work, keep the correction and any required retest together so a later reader can follow the disposition.
On a multi-building job, match the report to the building and phase listed for final inspection. A report bearing only the development name can leave the owner guessing which roof was tested. File the authority’s inspection result alongside it. Use the Guild guide to Florida tile approvals for the separate product-document check.