The carpenter’s drawing sets the top of the fascia. A later roofing schedule adds a ventilating strip along its upper edge. Both documents can look complete in isolation. Bring them together and there is a new question. Where will the first tiles actually bear?
Marley’s concrete plain-tile eaves detail uses a short undercourse beneath the full eaves course. Its guidance specifically asks the installer to account for an over-fascia strip ventilator when working out the pitch of that course. If a new component raises the bearing surface while the batten stays in place, it changes the tilt of the supported tile. Measuring how far the tail projects above the gutter will not, by itself, settle whether the courses align.
Put both revisions on one section
Ask for a section through a full tile, showing the fascia top, proposed ventilator, actual tile bearing, supporting batten and the following course. Label which surface the carpenter’s height dimension ends on. Ask the roofer to check the proposed assembly against the tile maker’s detail before the fascia height is repeated along the building. A short ground-level sample section with the chosen parts lets the two trades see the effect together.
Keep the vent product and revision on the agreed section. If a different strip arrives, compare its installed dimensions before releasing it for use. The check concerns the shape of the first course. Whether the vent delivers the required airflow is a separate design question. For the adjoining components, see the tile eaves, fascia and gutter guide.