A freight quote can get the entire clay tile order to the pavement while leaving a full day of vertical transport out of the bid. That distinction mattered at the Hotel Marshall in Texas. Ludowici’s account of the Spanish barrel tile restoration identifies Jeff Eubank Roofing Co. as the installer and describes a scaffold-mounted hoist with a 2,500-pound capacity serving a work area about 180 feet above the street.
For an estimate on another building, start with the number of pieces the contractor’s approved handling plan allows per trip. Suppose the plan allows 80 field tiles per trip and one section needs 650. Eight loads deliver 640. The last ten still need a ninth trip unless the crew can place them on another approved load. Add the ridge and eave pieces separately if they travel in different containers.
Price the trips in both directions
Ask who will stage the containers, load them, receive them at the work level and bring the empties down. If removal debris also travels on the hoist, agree on its time slots before counting the trips available for new material. A delivery timetable can look workable on paper and still give two crews the same morning slot.
Have the party responsible for lifting confirm the allowable gross load and configuration for the equipment on this job. Keep the trip count alongside the tile and fitting quantities so a change to the roof order reaches the logistics estimate.