Preserving the craft. Building its future.

Clay tile · Flashing orders

How much wall does a length of lead apron actually cover?

Account for the joints when pricing a lead apron across the upper edge of a clay-tiled lean-to.

By the Slate, Tile & Metal Guild ·

A clay-tiled lean-to ends against a straight masonry wall. The roofer needs an apron across the tops of the tiles. The estimate lists the exact length of the wall in lead sheet. Before releasing the order, ask where one piece of the apron will overlap the next.

In its UK top-edge abutment detail, Marley specifies individual Code 4 lead pieces up to 1.5 m long and laps of at least 100 mm. Its guide explains why the sheets are divided into lengths and the joints must accommodate movement. A single continuous strip is a different detail even if its overall length matches the drawing.

Check the joint count on the elevation

For a hypothetical 4.4 m straight wall, three 1.5 m pieces provide 4.5 m before joining. Two 100 mm overlaps reduce the net cover to 4.3 m. The order is already short before considering either end. Four pieces with three joints at that lap would need 4.7 m of combined cut length to span the wall. The roofer should lay out workable piece lengths and add the actual end details and any greater lap required.

Mark the piece ends on the wall elevation. Use a separate section to show the upstand and the distance the apron dresses down over the tile profile. Those dimensions set the sheet width. Adding them to a wall-length takeoff leaves the shop guessing what to cut. If this junction also carries a high-level ventilation opening, have the designer show the two details together before approving the apron.

Further reading

Marley · Roofing Sitework Guide, Flashings and Weatherings, pp. 24–25. This example uses the UK manufacturer’s top-edge lead detail. Confirm material, joint allowance, exposure and end treatments for the actual wall.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles