“Freight included to the job address” answers where the truck is going. A separate question remains for the superintendent who booked the delivery slot. When the truck arrives, who has agreed to take the pallets off it?
Ludowici’s published customer terms provide a concrete example. Unless the parties arrange otherwise, the buyer provides suitable labor and equipment for unloading and bears the unloading cost. The freight provisions also describe shipments arriving without a means to unload them unless agreed otherwise. Check the terms on your own order and any written exception before assuming what the carrier will bring.
Resolve the gap before dispatch
Send the supplier and receiver the delivery point and ask for the planned truck type, package count, dimensions and heaviest package weight. The receiving contractor can then confirm whether its equipment, operator and access suit the actual load. Ask where the carrier expects to stop and where the contractor expects to leave the material. A bid for unloading at the street can still exclude moving pallets to a courtyard.
Write the receiver’s name, arrival window and agreed set-down location on the booking. If the carrier changes the truck or the site loses access, give the dispatcher one person who can reschedule before the truck arrives. For comparing prices, keep line-haul freight, unloading and on-site movement on separate lines. Once the material is received, use the Guild’s tile receipt guide to document the condition and identity of the shipment.