A set of tender drawings shows a two-storey building. The construction drawings add a storey, keep the same clay plain tile and retain the same roof pitch. A buyer comparing product names would see no change. The designer checking the fixing schedule has a different question: which building did the calculation describe?
Marley explains that its UK fixing specification accounts for building height, roof design, local topography and wind exposure as well as the product. In its plain-tile example, the calculated specification can require fixing at closer course intervals than the stated minimum. This makes the schedule a project document with identifiable inputs.
Find the drawing that supplied the inputs
Read the location and building height on the calculation alongside the approved elevation. Check whether one schedule covers several blocks with different heights or exposures. Mark each mismatch, including any revision to the roof geometry, and return it to the responsible designer. A contractor should be able to tell which dated schedule applies to each roof before ordering fixings.
For work in the United States, the responsible designer should use the applicable local criteria and product documentation. Keep the resulting schedule and the drawing it references in the clay tile submittal. If a later drawing changes the building again, those two records identify precisely what needs review.