Two bids for a plain clay tile roof show the same field tile quantity. One allows roughly twice as much horizontal batten as the other. Before calling either estimator, look for two words on the roof section: crown cover. In this arrangement two layers of tile share a batten. In the field of a double-covered roof the successive courses hang on successive battens.
Read across one pitch column
Consider a simple 42-degree roof using the 18 × 38 cm plain tile described in CREATON’s application guide. In the 40–45 degree column the guide gives 155 mm between battens for double cover and 310 mm for crown cover. The tile requirement is approximately 35.8 per square metre. The wider batten interval in the second arrangement still has two layers of tile to carry.
For a hypothetical 20-square-metre field, that table gives about 716 tiles before cuts, fittings and reserves. A drawing that switches to crown cover and cuts the tile order to 358 has halved the wrong quantity. Likewise, carrying over the old batten order without checking the cross section can leave a misleading timber allowance. The guide provides separate batten sizing information for each covering method.
Have both bidders mark the covering method on the same slope section. Record the roof pitch, tile dimensions, batten interval and cross section there. Ask each bidder to show the first and last courses separately. A field quantity can agree to the tile while the two bids still describe different roof constructions. Keep the agreed section alongside the clay tile roof handover records for future repairs.