On a slate reroof with a built-in gutter, a shop drawing may show a continuous trough around the cornice. Look at the delivery plan as well. A long run can arrive as separate lengths that become a continuous liner only after the sheet-metal crew joins them in place. A shop inspection cannot establish the condition of a seam that has yet to be made.
The Copper Development Association recommends fabricating the liner outside the gutter framing where practical. This gives the fabricator access for soldering, inspection of the seams and a watertightness check before final installation. Ask which sections of the proposed liner can receive that check. A long corner piece may have different handling and access constraints from a short straight length.
Mark what will still be open on delivery day
Give each shop-made length a mark that appears on its drawing and inspection record. Circle the joints to be completed at the building in a different color. If the fabrication shop changes a splice location to suit transport, update that drawing before the crew fits the piece into the cornice. A photograph of a finished shop section can then be connected to the right length on the building.
Agree who will inspect the site connections and when the slater can cover the adjoining apron. The designer should specify a suitable test for that stage and record what area it covers. A passed shop check applies to the tested piece. The field joints and the completed roof-to-gutter transition still need their own review. See the Slate Roofing USA guide to built-in gutters for the surrounding eave assembly.