An estimate for a tiled addition lists a stepped cavity tray “at every course.” Which course? The roofer counts rows of concrete tiles up the slope. The bricklayer counts horizontal bed joints in the wall. For Timloc’s UK Everdry stepped brickwork system, the wall sets the count. Changing the tile gauge on the drawing does not change the number of masonry joints crossed between the same two elevations.
Write the direction beside the dimension
Take a hypothetical abutment that rises 1,350 mm from its low point to its high point. With a 75 mm brick coursing height, that is 18 course intervals along one side. The same 1,350 mm taken with a tape laid along the sloping roof would represent a smaller rise. Timloc gives separate table factors for horizontal and sloping measurements. Label the dimension before anyone transfers it to an order sheet. On existing masonry, have the surveyor check actual bed joints at the ends, especially where a course changes height.
Convert the count into a list the merchant can check
Draw the abutment as seen facing the wall and mark the low and high ends. Timloc distinguishes the handed intermediate runs, starters for different wall endings, and a ridge tray where opposing slopes meet. Show whether the low end meets the middle of a wall or turns a corner. Ask the supplier to identify the starter, intermediate components and any ridge piece separately, reconciled to the marked elevation. Eighteen course intervals alone cannot tell a merchant which eighteen positions those parts occupy.
Record the roof pitch, cavity width and masonry coursing alongside the drawing. Before ordering, check that the outlet at the foot of the run will discharge clear of the finished tile profile. The tray count and the outlet detail answer different questions on the same elevation.