A designer reviewing the roof mockup would like more of the raised barrel accents. The field tile stays the same. What should the architect send the structural designer before the revised pattern goes into the finish schedule?
Westlake Royal’s guide specification gives installed tile weights for several densities of its Boosted Barcelona concrete profile. The 10 percent application is listed at 945 pounds per roofing square. The 30 percent application is 1,050 pounds per square. Both numbers include the field tile. Adding either number to a separate field-tile weight would count the base covering twice.
Put the change on the slope where it occurs
Imagine a revision that affects eight roofing squares, or 800 square feet of actual sloped roof area. The difference between the two listed configurations is 105 pounds per square. Across those eight squares the proposed finish adds 840 pounds of tile, an average increase of 1.05 pounds per square foot across the changed area. A neighboring slope that keeps the original pattern contributes nothing to that increase.
Attach the marked elevation, affected area and both product rows to the change request. Identify any separate bedding, supports or other components included in the project assembly. The structural designer can review the change in its actual location. For the purchase order, the companion guide to counting barrel accents addresses a separate quantity: the number of additional pieces to buy.